10/9/2013 - *Tanglewood Drive Reconstruction Notice

October 8, 2013

Re:   Notice of Start of Construction
         Tanglewood Drive Reconstruction                

Dear Property Owner:

The Town of Canton will begin construction of roadway improvements on Tanglewood Road from Morgan Road to East Hill Road on or about October 15, 2013. The roadway improvements will include minor drainage improvements, reclamation or reconstruction of the existing bituminous concrete pavement section, resurfacing of the roadway, curb replacement, and reconstruction of driveway aprons as required.

The roadway will be open to local traffic at all times during construction.  Residents using Tanglewood Road may experience delays during completion of the project.  Detours signs will be provided during construction activities to reduce traffic congestion during construction. 

Driveway aprons to your property may be replaced within the public right of way so that they will be consistent with the elevation of the new roadway pavement surface.   The contractor for the project, Canton Village Construction Company, is required to coordinate any temporary closures of your driveway in advance of completing the removal and replacement of any driveway aprons.  There may, however, be minor delays in leaving or entering your driveways during certain times of the day.   

We appreciate your patience during the completion of the project.

If you have any questions, do not hesitate to contact Jeff Shea, Project Administrator, at jshea@townofcantonct.org or tel. 860-693-7855.